Free corrective action plan template for D5/D6/D7 of the 8D process, with verification tracking, effectiveness monitoring, worked example and FMEA update che...
Corrective actions fail for one reason more often than any other: nobody defined what "fixed" means before implementing the fix. This template gives you the three tables that make a corrective action auditable — a verification plan (D5), an implementation plan (D6) and an effectiveness monitoring plan (D7).
Use it whenever you close out an 8D report, respond to a SCAR, or manage a CAPA record under IATF 16949 or ISO 9001.
Before full implementation, prove that the action actually addresses the root cause.
| Action | Success Criteria | Test Method | Sample Size | Result | Status |
|---|---|---|---|---|---|
| (Example) New seal material | 0 leaks after 1,000 h | Pressure decay test | 30 units | Pending | Open |
Rules for a good D5:
Once verification passes, roll the action out with owners, dates and risks.
| Action | Owner | Due Date | Resource Needed | Risk Assessment | Status |
|---|---|---|---|---|---|
| (Example) Update SOP | QE Lead | Week 4 | 2 hours | Low | Open |
Rules for a good D6:
Verification proves the fix worked in a test. Monitoring proves it keeps working in production.
A corrective action is only verifiable if the success criterion is measurable.
| Weak | Strong |
|---|---|
| Improve sealing | 0 leaks in 1,000 h on 30 units |
| Reduce defects | Defect rate < 50 PPM over 3 consecutive lots |
| Train operators | Post-training audit score >= 95% on 20 operators |
If you cannot express the criterion as a number or a pass/fail test, it is not ready for D5.
A pump housing seal leaks at end-of-line leak test. The team traces the root cause to a seal compound that hardens below the specified operating temperature. Here is how the three tables fill in.
D5 verification. The proposed action is a new seal compound. Success criterion: 0 leaks after 1,000 h at −20 °C to +90 °C cycling. Test method: pressure decay test at 1.5 bar, leak rate limit 0.5 cm³/min. Sample size: 30 units from an independent production lot, not the lot that failed. Result recorded as measured values per unit, with the worst-case unit called out explicitly.
D6 implementation. Actions: update the seal drawing and supplier specification (owner: Design Engineer, week 2); qualify the new compound with the supplier (owner: SQE, week 3); revise the incoming inspection plan (owner: QE Lead, week 4); update the SOP and retrain the line (owner: Production Supervisor, week 5). Each row carries a single name, a date and a risk note — the new compound is harder, so assembly force may rise and a new damage mode must be watched.
D7 monitoring. 30-day check: 100% leak test on all units, zero escapes. 90-day check: defect rate below 50 PPM over three consecutive lots. 12-month check: field return rate compared with the pre-fix baseline. FMEA and control plan updated, and the same seal family on other models reviewed for horizontal deployment.
Before signing off, confirm that each D5 row has a numeric criterion, a method and a measured result; that each D6 row has one owner, one date and a risk note; and that each D7 row has a date, an owner and a recorded outcome. Cross-check that the FMEA and control plan revision numbers changed where the action required it, and that the monitoring sample is drawn from normal production, not from a hand-built trial batch.
D5 depends on a verified D4 root cause — if the cause is still a guess, the verification plan tests the wrong thing. D6 depends on a passed D5; implementing before verification turns a trial into a production risk. D7 feeds back into D2 problem description and D4 analysis: if monitoring shows recurrence, the root cause was incomplete and the 8D reopens rather than closing. D7 also feeds the FMEA and control plan, which is how the lesson survives the next staff change.
→ Skip manual planning — the free AI 8D Generator at report.8d.wiki drafts corrective actions, owners and verification plans for you.